B&J Catalano | New Tailings Storage Facility (TSF) Re-Instatement

Client | B&J Catalano
Project | TSF Lift Pipeline Re-Instatement
Location | Golden Grove, Yalgoo WA
Project Profile
Scope

Relocate pipe for tails dam lift and reinstate

Pipe Work

• Install 25 Sweep Bends and 13 reducers
• Install 52 x 160mm 6m lengths

Contract

Day rates

 

Additional Works

• Lift pipe from temporary wall onto new wall
• Install all droppers and spigot clamps
• Supply and install 1,200m of DN170 Mega Flo for seepage
• Install DN160 seepage outflow pipes around the dam
• Installation of spigot droppers

Services and Equipment Provided

• Supervisor, Polywelder and Operators
• Supervisors vehicle and welding truck c/w generator
• 2 x Manitou Telehandlers and spreader bars
• 8.5 ton Excavator and pipe roller slings
• 3 x HF350 Polywelders
• Extrusion welders

 