GNT Resources | Borefield Installation
Client | GNT Resources
Project | Primary Borefield Installation
Location | Dalgaranga, Murchison WA
Project Profile
Scope
Install 10.5km Borefield Pipeline
Pipe Work
• 8.1km 315mm PN8
• 600m 355mm PN8
• 1.8km 280mm PN10
Contract
Day rates
Additional Works
• Harvest and load 150 x 315mm PN10 x 20m lengths
• Unload and stock pile pipe along the pipeline corridor for station welding
• Supply, fabricate and install 9 pipeline breather tee’s
• Connect bore headworks
• Install culvert at road crossings
Services and Equipment Provided
• Supervisor, Polywelder and Operators
• Supervisors vehicle and welding truck c/w generator
• 2 x Manitou Telehandlers
• Tracstar 500 Polywelder and data logger
• 2 x Polyhorse pipe racking system with Power Assist
• 2 x HF350 Polywelders
• Sea Container storage facility